
Project list Cinemas
ASTOR Grand Cinema, Hanover
Quality management,organisation of contracts and invoices
Construction costs: € 10 million
2014
UCI Cinema Centre Ruhr Park, Bochum
Structural survey, construction documentation, tender, award of contract, project supervision of the entire renovation of the extended interior fittingsTotal interior design and architecture costs: € 5.2 million
2004
Cinestar Cinema Centre, Rostock
Project supervision of the extended interior fittingsTotal interior design costs: € 1 million
2000
Cinestar Cinema Centre, Stralsund
Tender for interior design and architectureTotal interior design costs: € 4 million
2000
Sony Centre Imax and Cinema Complex Potsdamer Platz, Berlin
Tender, project supervision of the extended interior fittingsTotal interior design costs: € 6.7 million
1999
Cinestar Cinema Centre, Hannover
Project supervision of the extended interior fittingsTotal interior design costs: € 1 million
1999
CinemaxX Cinemacenter Potsdamer Platz, Berlin
Tender, award of contract and project supervision of the extended interior fittingsTotal interior design costs: € 6.4 million
1998
Cinestar Cinema Centre, Bremen
Project supervision of the extended interior fittingsTotal interior design costs: € 1 million
1998
Cinestar Cinema Centre, Fulda
Project supervision of the extended interior fittingsTotal interior design costs: € 1.3 million
1998
Cinestar Cinema Centre Zagreb
Coordination of the entire project for the tenantTotal project costs: € 17 million
1998
CinemaxX Cinema Centre Wuppertal
Support of the local project supervision, quality assuranceTotal interior design costs: € 4.5 million
1997
CinemaxX Cinema Centre Essen
Tender, award of contract and project supervision of the renovationTotal interior design costs: € 1 million
1996